North Cyprus Property Victim “Hildy” responds to Cafer Yucelgazi’s claim for Incesu “extras”

EXTRA’S from THE IMAGINATION OF CAFER YUCELGAZI.

In ‘ONCE UPON A TIME LAND’

 a FAIRY STORY WRITTEN BY PAULINE READ

 (Translated by ITV For Holiday Homes from Hell.)

 [Handwritten]

 ADDITIONAL WORKS FOR VILLA NO. 10                                                                      *

Pool Radial* Mould 48m² x 16TL                                                                 = £333.-

    “      “      Concrete 135m² x 0.40 = 54m³ concrete x 105TL             = £2,465.-

    “      “        Iron 4 tons x $850                                                                       = £2,217.-

    “      “        Iron labour x 4 at 400TL                                                           = £695.-

 

Pool Columns Mould labour at 12 x 4.5m²      54m² x 16TL                 = £375.-

          (LOWER)    “         “    at 12 x 4.5           54m² x 16TL                         = £375.-

    “      “     Concrete at 6m³ x 105 TL                                                               = £273.-

    “      “     Iron at 1 Ton x $850                                                                       = £554.-

    “      “       “     labour at 1 x 400 TL                                                              = £173.-

                                                                                                                        _______

                                                                                                                        £7,460 – (A)

Interior section of the house:

In the living room and upstairs bedroom

PVC windows extended to below      Difference                                                            £1,000.-

Natural marble used for all inside

and outside terraces of the house.  Difference at 24TL  x 300m²                                          = £3,130.-

Excavations + corrections + fills relating to the place where the house will stand        = £3,000.-

Mould work for front load-bearing radial at 46m² x 16 TL                                              = £320.-

Concrete for                 “        “         “      at 16m³ x 105TL                                            = £730.-

Iron for                         “        “         “       2.5 TON x $850                                           = £1,386.-

Labour for                    “        “         “       iron at 2.5 x 400 TL                                     = £434.-

Labour for                    “        “       wall mould at 168m² x 16 TL                                  = £1,168.-

Concrete for                 “        “         “      at 20m³ x 105 TL                                           = £913.-

Iron labour for              “        “         “       2.5 TONS at 400TL                                      = £434.- 5/9

[Illegible] Foundation Radial Concrete Difference at 25m³ x 105 TL                                 = £1,141.-

                                                                                                                        ________

                                                                                                                        £13,656 (B) 

* tr. Author has used the English word ‘radial’ throughout in original Turkish text which has been left unchanged.

[Handwritten]

House no.      10

Rear Retaining Wall:

Labour for mountain stone 100m² at 25TL                              = £869.-

5 Lorry-loads of stone      5 x at 450 TL                         = £978.-

Materials 100 bags of cement + 3 Lorry-loads of Sand        = £1,000.-

Bulldozer labour                                                                             = £200.-

                                                                                                            ________

                                                                                                            £3,047. –    (C)

Front load-bearing wall side stairs                                            £   992

                                                                                                            ________

                                                                                                            £4,039  

______________________________ / _____________________________

                                                Grand Total                          £ 7,460. –   (A)

                                                                                                £13,656. – (B)

                                                                                                £ 4,039. – (C)

                                                                                                ___________                                   

                                                                                                £25,155.-

                                                                                                £18,866.-

                                                                                                ___________                                                              

                                                                                                £44,021. –  *

                                                                                                =========

The builder is in LaLa land  and they are still looking for the Wicked Witch who is said to be somewhere in a place called ‘Forum’.

Now go to sleep children and the nasty witch will not get you !!!!!!